Excavation, Concrete
Demolition, UST Removal including Transportation, and Disposal
of Soils contaminated with petroleum hydrocarbons
Work Description
– General:
Chase Environmental Group
(Chase) was contracted by the Commonwealth of Kentucky,
Finance and Administration Cabinet, Division of Engineering
to provide asbestos, mold abatement and demolition services
at the KCTCS Maysville Community College. The complete demolition,
abatement and renovation were conducted over summer break
in preparation of the students return.
Interior Demolition: Ceiling
panels, ductwork, water lines, floor coverings, drywall,
air handling units, heating units were removed.
Asbestos abatement—Asbestos
containing materials (ACM) encountered during the demolition
activities were removed and disposed.
Maysville
Community College
Mold abatement—After
interior demolition activities were completed, mold contamination
was removed by HEPA vacuum, TSP application, wiping and
rinsing all interior surfaces of the building. “Enviroshield”
mold inhibiting paint / encapsulant was applied in all areas
above the drop ceilings and testing was performed to assure
removal was complete.
Chase’s portion of
the project was completed in 75% of the allowed contract
time at 88% of the proposed estimate.
Location:
Maysville Community College, Maysville, Kentucky
Regulatory Basis:
Special Waste / OSHA /confined space